How to Plan Network Points and Server Room Layout for a New UAE Office
Plan network points and the server room before the fit-out drawings are final. Allow two points per desk, plus extra for Wi-Fi, cameras, printers and meeting rooms. Add 20 to 30 percent spare. Put the server room in a central, lockable space with its own power and cooling. Changes made later cost far more.
Introduction
Planning network points and server room layout for a new UAE office is easy in week one of a fit-out. It is painful in week twelve.
Once ceilings are closed and floors are finished, every extra cable means drilling, dust and delays. We see this often. A team moves in, and half the desks have no port. The server sits in a storage cupboard that overheats by noon.
This guide shows you how to avoid that. You will learn how many network points you need, where they should go, and what a small server room must include.
Xedos Technologies has set up office networks across the UAE since 2013. The advice below comes from that work. Share it with your fit-out contractor before drawings are signed off.
When Should You Plan Network Points in a New UAE Office?
Plan network points during the design stage, before the fit-out contractor finalises ceiling, power and partition drawings. At this point, cable routes and outlet positions can still change at no extra cost. Once walls close, every added point means rework.
Fit-out teams work in a fixed order: partitions, ceiling grid, power, then finishes. Cabling must sit inside that order. If your IT partner joins after the ceiling is up, routes get compromised.
Your building may also need management approval for cabling works. Ask early for the base-build specification and the rules on risers and containment.
Here is a simple rule. Share the furniture plan, headcount and growth plan with your IT partner at the same time as the architect. Our office IT setup checklist shows where this step sits in the full project.
A free site survey is the best first step. Our engineers walk the floor plan and mark every outlet before work starts.
How Many Network Points Does Each Employee Need?
Plan at least two network points per desk. One serves the computer. The second serves a phone, a docking station or a future device. Then add dedicated points for access points, cameras, printers, meeting rooms and reception, plus 20 to 30 percent spare.
A 25-person office needs far more than 25 points. Here is how the count builds up for each area.
| Area | Typical points |
| Desks | 2 per person |
| Wi-Fi access points | 1 per 150 to 200 sq. ft. of open space, ceiling mounted |
| CCTV cameras | 1 per camera position |
| Printers and copiers | 1 each |
| Meeting rooms | 3 to 4 per room (display, camera, table, spare) |
| Reception | 2 to 3 |
| Biometric attendance device | 1 per device |
| Wall displays and digital signage | 1 each |
Let us run the numbers for 25 staff. Desks need 50 points. Add four access points, four cameras and two printers. Two meeting rooms take eight points. Reception, one attendance device and two displays add five more. That is 73 points.
Add 25 percent spare and you reach about 90 points. That spare capacity costs little today. It saves a costly retrofit when you hire your 30th employee.
Do not skip the growth margin. In our experience, headcount in a new UAE office often rises within the first year.
Your attendance device also needs a port at the right height. Our guide on biometric attendance for a new office covers the power and network points it needs.
Where Should Network Points Go?
Place desk points where furniture will actually sit, and put access points on the ceiling, not on walls. Mount points on columns and perimeter walls too. That way a layout change does not strand a desk without a port.
Open-plan floors change often. So think in zones, not just desks. A grid of floor boxes or perimeter outlets handles most rearrangements.
Here are the placement rules we use:
- Desks: Put the double outlet at desk height or in a floor box under the desk block.
- Access points: Mount each one on the ceiling, with a dedicated cable run. Plan the positions from a coverage survey, not guesswork.
- Meeting rooms: Add a floor box under the table and a wall point behind the screen.
- Cameras: Place points at ceiling height near entries, reception and the server room door.
- Printers: Put points in print bays, not in the middle of work areas.
Keep every cable run to 90 metres or less from patch panel to outlet. Longer runs lose signal quality and fail testing.
Next, choose the cable type. Cat6 handles gigabit speeds to the desk and suits most small offices. Cat6A costs more but carries 10 Gbps. It also handles the high power that newer Wi-Fi access points draw over the cable.
If your office will grow or use newer Wi-Fi, Cat6A for access point runs is a smart choice. You will not want to pull those cables twice.
Our structured cabling services cover design, installation and certification, so every point is tested and labelled.
Where Should the Server Room Go in a New Office?
Choose a central, lockable room away from water pipes, pantries and glass walls. It should sit close to where the internet lines enter the building. Leave space for growth, because a server room that is too small is hard to enlarge later.
A central position keeps cable runs short and below the 90 metre limit. It also keeps every floor area within reach.
Avoid these spots: rooms under bathrooms, rooms with outside walls in direct sun, and storage cupboards with no cooling. Dubai heat makes the last one especially risky.
Think about the internet lines too. Most offices want two providers, such as e& and du, for backup. Both lines should arrive at the same room. Ask the building management where the telecom ducts enter, then plan the server room near them.
The room should have a solid door with a lock and no other use. Do not share it with stationery or spare furniture.
Access matters as well. Only IT staff and your partner should hold keys. For offices that handle sensitive data, add a card reader or biometric lock.
What Should a Small Server Room Layout Include?
A small server room needs a rack or cabinet, patch panels, switches, a firewall, a UPS, labelled cable pathways, a dedicated power circuit and clear working space. Plan about one metre of free space in front of and behind the rack.
Here is a simple size guide we use at the planning stage:
| Office size | Rack | Room size to plan |
| 10 to 25 staff | One 12U to 18U cabinet | About 2 m x 2 m |
| 25 to 60 staff | One 42U rack | About 2.5 m x 3 m |
| 60 to 100+ staff | Two racks | About 3 m x 4 m |
These are starting points. Servers, storage and growth plans change the answer, so confirm during the site survey.
Now the layout inside the rack. We build from top to bottom in a set order: patch panels first, then switches, then the firewall, then servers, then the UPS at the bottom. Heavy items sit low. Network gear sits high, near the incoming cables.
Good cable management is not cosmetic. Messy cables block airflow and make faults hard to trace. Every cable should carry a label at both ends that matches your port map.
A few more must-haves:
- A dedicated power circuit, separate from the office sockets, so a kettle never trips your servers.
- A UPS sized for your equipment with enough runtime for a safe shutdown.
- Cable trays or ladder racking above the rack, not loose cables on the floor.
- A fire extinguisher suitable for electrical equipment, placed near the door.
If you plan to run on-site servers, our server and network support team can size the room and build the rack.
How Do You Cool and Power a Server Room in the UAE Heat?
Give the server room its own dedicated air conditioner, sized to the equipment heat load, and keep it between 18 and 27°C. Put the cooling on backup power too. A UPS keeps servers running, but without cooling they overheat within minutes.
This is the most common gap we find. The office air conditioning switches off at night or on weekends. Servers keep running, and the room heats up fast.
For a small room with one or two servers, plan roughly 5,000 to 10,000 BTU of cooling. Larger rooms need more. Add a safety margin of 20 to 30 percent for UPS losses and future equipment.
Use a split unit made for continuous operation. A standard office unit is not built to run around the clock. Where possible, install two units so one covers if the other fails.
Humidity matters too. Aim for roughly 40 to 60 percent. Too dry and static builds up. Too damp and parts corrode.
Add a simple temperature sensor that sends alerts to your IT partner. You will know about a cooling failure before the servers do. An IT AMC can include this monitoring.
Five Planning Mistakes We See Before Handover
Most problems we find come from rushed planning, not bad equipment. These five mistakes show up again and again.
- Using a storage room as the server room. It has no cooling, no lock and no growth space.
- No ceiling points for Wi-Fi. Access points end up on walls or in cabinets, and coverage suffers.
- Counting desks, not devices. Printers, cameras and meeting rooms get forgotten.
- Sharing the power circuit. One overloaded socket can take down the network.
- No testing or documents at handover. Nobody knows which port goes where, or if it passes.
The last one matters most. Ask for a certification test report for every point, plus a port map and network diagram. If you later switch IT partners, those documents save days of work.
Already living with poor cabling? Read our guide on the signs your office cabling needs an upgrade. And if the network already feels slow, see why office networks run slow.
Conclusion
Planning network points and your server room layout early is one of the cheapest decisions in a fit-out. Count devices, not just desks. Add spare capacity. Put the server room in a secure, central, cooled space with its own power. Test every cable before you move in.
Xedos Technologies has planned and built office networks across Dubai and the UAE since 2013. Our new office IT setup service starts with a free site survey and a floor plan marked with every point. Structured cabling starts from AED 150 per certified point, and you receive an itemised quotation within 48 hours.
Call or WhatsApp +971 52 607 3989, or contact our team to book your survey before the drawings are signed.
FAQ
How many network points do I need for 20 employees?
Plan about 40 points for desks, two per person. Add points for access points, cameras, printers, meeting rooms and reception. Then add 20 to 30 percent spare. A 20-person office usually ends up with 60 to 75 points in total.
Can I use a storage room as a server room?
Only if it meets the same needs as any server room. It must have dedicated cooling, a lock, its own power circuit and room around the rack. Most storage rooms fail on cooling. Heat is the main cause of early equipment failure in the UAE.
How much space does a small office server room need?
A small office of 10 to 25 people can use a cabinet in a room of about 2 m by 2 m. Leave about one metre of working space at the front and back of the rack. Larger offices need more, so confirm during a site survey.
Should network points be Cat6 or Cat6A?
Cat6 suits most desk points in small offices running gigabit speeds. Cat6A is better for access point runs and for offices planning faster networks. It costs more now but avoids pulling new cables later.
Does a small UAE office need a server room at all?
Not always. A small team that works fully in the cloud may only need a wall-mounted cabinet with a switch and firewall. If you run on-site servers or storage, a proper server room is the safer choice.